Workplace 6 at Darling Island: A Six Greenstar Building

Back to Technical Insights
Buildings & StructuresBuilding StructuresNew South Wales
30 June 2019
Tonkin (formerly known as TLB Engineers) was appointed to carry out the consulting structural engineering design and documentation of the $50m six storey office building, ‘Workplace 6’, in Pirrama Road opposite the Star City Casino in Darling Island, Pyrmont. In 2008 it was awarded the first Six Star rating for a NSW building from the Green Building Council of Australia.

An important element in achieving a Six Star rating was the requirement to reduce the Portland cement content and use recycled cementitious materials and recycled aggregates in the concrete. Usually the replacement of normal Portland cement with fly ash and slag reduces the early strength development of concrete (Ref. 1). As the floor slabs were to be post-tensioned, there was consequently a concern about an increase in the risk of concrete failure at the dead end and live end anchorage zones at the time of initial stressing, usually carried out 24 hours after pouring the concrete.

This report briefly describes the test programme carried out to check the early strength development of alternative green concrete mixes and to test the posttensioning dead end anchorages in model slabs at 24 hours, The aim was to reduce the risk of concrete failure when the initial stressing loads were applied.

The success of this Tonkin test programme resulted in the use of a ‘three star’ concrete for the post-tensioned floor slabs, which contributed to the achievement of a Six green Star rating for the building.

The Structure
Construction commenced in March 2007 and the building was completed in 2008. It is a reinforced concrete framed structure supported on piles up to 15m deep to rock with post-tensioned one-way banded concrete floor slabs.
The column grid is generally 8.0m x 12.0m with a typical floor plan area of 3,600m2. 

The six story building has a gross floor area of 18,000m2.

The Concrete
The main structural element in contributing to the Six Star rating for the building was the concrete, which was to have a significantly reduced Portland cement content and a reduced natural aggregate content.
This was to be achieved using increased fly ash in the concrete mix as well as blast furnace slag.

The specified concrete strength was 32 MPa at 28 days, which is typical for posttensioned slabs, with 7 MPa (min.) required for the first stage stressing at one day of age, and 22 MPa (min.) required for the second (and final) stage stressing at five days of age.

In addition to the concern that the concrete may not achieve sufficiently high early strength to minimise the risk of slab failure under the applied prestressing load, there was also doubt about the use of standard laboratory cured concrete cylinder sample compression tests to adequately represent the strength of the concrete in the actual floor slabs.

The Concrete Test Programme
Tonkin developed and supervised a test programme to be undertaken using three 32 MPa concrete mixes and six model slabs to assess the effects of recycled cementitious materials and recycled aggregates on the anchorage capacities of post-tensioned tendons at initial stressing. Each of the concrete mixes included a range of recycled cementitious and aggregate materials.
Table 1: Summary of Test Results
Figure 1: Compressive Strength Test Results

Author

Peter J. Taylor & Andrew J. Sutton